Project Complete

Introduction to forthcoming works 

Planned road closures and diversions from 22nd September 2022

Please see below for information regarding our latest works at Bognor Road and a letter to local residents here: September 2022 letter of introduction

We thank you for your co-operation and patience during this time and want to reassure you that we will do all we can to minimise disruption. If you have any questions or comments, then please do not hesitate to contact Mark Hill or Nicki Main.

 

Scheme Phasing and Road Closures

The project will be undertaken in three phases – the phased plans and road closures are shown below.

Works planned on A27 in May and June 2023 – ALL works are being undertaken at night time from 8pm to 5.30am

TTRO1 Specific location and extent of required restriction: Adjacent A27 roundabout, Eastbound Full road closure (Lane 1 & 2 closure)

Proposed start date of works or event: 09.5.2023
Proposed finish date of works or event: 13.5.2023

TTRO2 Specific location and extent of required restriction: Adjacent A27 roundabout, Lane 1 and 2 Westbound full road closure

Proposed start date of works or event: 15.5.2023
Proposed finish date of works or event: 20.5.2023

TTRO3 Specific location and extent of required restriction: Adjacent A27 roundabout, Lane 1 and 2 Westbound full road closure

Proposed start date of works or event: 5.6.2023
Proposed finish date of works or event: 14.6.2023

TTRO4 Specific location and extent of required restriction: Adjacent A27 roundabout, Lane 1 and 2 Eastbound full road closure

Proposed start date of works or event: 14.6.2023
Proposed finish date of works or event: 21.6.2023

Temporary Traffic Regulation Orders are attached here for further information

TTRO 1 TTRO 2 TTRO 3 TTRO 4

If there is an emergency during this time:

24 hour emergency contact name: Scott Williamson
24 hour emergency contact phone number: 07425 758531

 

 

Works planned from week commencing 19th April 2023 for up to 5 days (estimated to be completed on 21st April 2023)

Please note, temporary closure of A259 Westbound, Oving CP, 19th April 2023, A259 Westbound between the Drayton Lane & Bognor Road Roundabouts.

The temporary closure is scheduled to commence on 19th April 2023 for up to 5 days (it is estimated to be completed on 21st April 2023) and is required for the safety of the public and workforce while Mildren Construction Ltd undertakes carriageway surfacing, white lining & the commissioning of traffic signals.

The restriction will be in place overnight only from 20:00 until 05:00.

An alternative route will be signed on site but please visit https://one.network/?tm=133169595 for more details.

For further information please visit this website link.

Works planned from week commencing 30th January 2023

  • Off peak lane closures Westbound lane 1 and 2 from 09.30 AM – 15.30 PM beginning on the 30th January for 6 weeks.
  • Works to include Bus Lay-by construction, Traffic light install, Ducting and street lighting, Drainage and utility diversion works.

Works planned from week commencing 12th December 2022 to April 2023

  • Current works will be completed as specified by the 16th December time for embargo – this means we will not be working on the road from 16th December through to 3rd January 2023 and all traffic management will be minimised.
  • Lane closures have been requested for week commencing 9th January 2023 until 7th April 2023. This work is weather dependent and may be cancelled at short notice.
  • Works early in 2023 will include Bus laybys/Kerbing/Traffic signals/Drainage/Ducting/Street lighting/Surfacing/Road markings and VRS barrier.

Week commencing 23rd November 2022

There will be lane closures in place on both east and west bound A259 over night during w/c 23rd November 2022. This work is weather dependant and may be cancelled at short notice.

Week commencing 31st October 2022

We are working nights all til Friday 4th November with lane closures east and westbound on the A259 Bognor Road. The lane closures will be in effect between 21.00 until 05.00 when we are carrying out surfacing and ducting installation.

Week commencing 24th October 2022

Please note the lane closure overnight on 24th October. Lane 1 A259 Eastbound will be shut between 20.00 – 05.00 AM.

Week commencing 19th September 2022

The Eastbound Road closure on the A259 is going ahead as planned on the 22nd September from 20.00 to 05.00 on 23rd September.

 

Road closure and diversion closure point

Phase 1 Drawing

Phase 2 Drawing

Phase 3 Drawing