Guildford Park Road Enabling Works – Newsletter 9

Mildren Construction Community Website
November 7th 2018

Welcome to our ninth Newsletter to tell you about our works. We will publish updates every 2 weeks, and as work progresses will include photos.

Progress in the last 2 weeks

  • Continue brickwork for king post wall
  • Completion of installation of all new drainage and services within site compound
  • Commence ground reduction, prior to placement of structural fill for new carriageway

Work next 2 weeks

  • Completion of ground reduction
  • Placement & compaction of structural fill for new carriageway
  • Laying of new kerbs and gullys within carriageway
  • Continue with brickwork for king post wall

 