Guildford Park Road Enabling Works – Newsletter 16

February 7th 2020

Welcome to our sixteenth Newsletter to tell you about our works.

Progress last 2 weeks;

  • Mobilisation of piling sub-contractor
  • Installation of 1st 30m of the sheet pile wall

Programme for the next 2 weeks;

  • Continuation/completion of sheet piling (90 linear metres total)
  • Commencement of micro pile installation