Guildford Park Road Enabling Works – Newsletter 8

Mildren Construction Community Website
September 13th 2018

Welcome to our eighth Newsletter to tell you about our works. We will publish updates every 2 weeks, and as work progresses will include photos.

If you have any questions or comments, please do not hesitate to contact me.

Please note; any dates given are subject to change as per the construction programme.

Progress last 2 weeks;

Completion of pre-cast concrete panels for king post wall. (inc. shingle backfill)
Completion of LV & Street Light ductwork within site compound

Work next 2 weeks;

Commence new storm and foul drainage within main site compound