Welcome to our seventh Newsletter to tell you about our works. We will publish updates every 2 weeks, and as work progresses will include photos.
If you have any questions or comments, please do not hesitate to contact me.
Please note; any dates given are subject to change as per the construction programme.
Outline of works
- Drainage (both surface water and foul)
- Construction of brick clad king post walls
- Installation of below ground services
- Forming of new roads and footways
- Reinforced earth bank retention
Progress last 2 weeks
- Installation of pre-cast concrete panels for king post wall. (inc. shingle backfill)
Work next 2 weeks
- Completion of pre-cast concrete panels for king post wall
- Commence new drainage within main site compound