Welcome to our sixth Newsletter to tell you about our works. We will publish updates every 2 weeks, and as work progresses will include photos.
If you have any questions or comments, please do not hesitate to contact me.
Please note; any dates given are subject to change as per the construction programme.
Outline of works
- Drainage (both surface water and foul),
- Construction of brick clad king post walls
- Installation of below ground services
- Forming of new roads and footways
- Reinforced earth bank retention
Progress last 2 weeks
- Complete installation of king post piles
- Final stage of tree clearing adjacent to Network Rail property boundary
Work next 2 weeks
- Installation of pre-cast concrete panels for king post wall