Guildford Park Road Enabling Works – Newsletter 6

Mildren Construction Community Website
August 9th 2018

Welcome to our sixth Newsletter to tell you about our works. We will publish updates every 2 weeks, and as work progresses will include photos.

If you have any questions or comments, please do not hesitate to contact me.

Please note; any dates given are subject to change as per the construction programme.

Outline of works

  • Drainage (both surface water and foul),
  • Construction of brick clad king post walls
  • Installation of below ground services
  • Forming of new roads and footways
  • Reinforced earth bank retention

Progress last 2 weeks

  • Complete installation of king post piles
  • Final stage of tree clearing adjacent to Network Rail property boundary

Work next 2 weeks

  • Installation of pre-cast concrete panels for king post wall

 