Welcome to our fourth Newsletter to tell you about our works. We will publish updates every 2 weeks, and as work progresses will include photos.
If you have any questions or comments, please do not hesitate to contact me.
Please note; any dates given are subject to change as per the construction programme.
Outline of works
- Drainage (both surface water and foul).
- Construction of brick clad concrete retaining walls.
- Installation of below ground services.
- Forming of new roads and footways.
- Reinforced earth bank retention.
Progress to date
- Continue new ducting installation for service diversions. (Within main site compound and along Guildford Park Church Road – North)
- Full depth reconstruction of Guildford Park Church Road footpath
- Complete installation of new ducting within existing car park.
Work next 2 weeks
- Continue installation of new ducting along Guildford Park Church Road
- Full depth reconstruction of Guildford Park Church Road footpath
- Construction of duct pits within site compound