Guildford Park Road Enabling Works – Newsletter 3

April 12th 2018

Welcome to our third Newsletter to tell you about our works. We will publish updates every 2 weeks, and as work progresses will include photos.

If you have any questions or comments, please do not hesitate to contact me.

Please note; any dates given are subject to change as per the construction programme.

Outline of works

  • Drainage (both surface water and foul).
  • Construction of brick clad concrete retaining walls.
  • Installation of below ground services.
  • Forming of new roads and footways.
  • Reinforced earth bank retention.

Progress to date

  • Tree felling along Guildford Park Church Road and adjacent to Guildford Park Avenue complete except nested trees and trees adjacent to Network Rail property.
  • Completion of temporary footpath on South side of Guildford Park Church Road.
  • Continue new ducting installation for service diversions. (Within main site compound and along Guildford Park Church Road – North).

Work next 2 weeks

  • Continue installation of new ducting within main site compound. And along Guildford Park Church Road
  • Commence installation of new ducting within existing car park.
  • Enabling works for CFA piling to new reinforced concrete wall.

 

Back to project View More Project News