Guildford Park Road Enabling Works – Newsletter 11

Mildren Construction Community Website
December 21st 2018

Welcome to our eleventh Newsletter to tell you about our works. We will publish updates every 2 weeks, and as work progresses will include photos.

Progress last 2 weeks

  • Completion of brickwork retaining wall
  • Continue structural fill placement, kerbing and road gullys

Work next 2 weeks (From 3rd Jan):

  • Completion of structural fill placement, kerbing and road gullys
    Surfacing works for new multi-storey car park access road
    Commence works for new compound and traffic management into car park