Please find all letters communicating information regarding our works at One Horton Heath. Please click the link within the accordion to download a copy of the latest letter.
19th to 26th July there will be two way signals on Burnetts lane as we close a lane to allow drainage works to be completed.
26th to 29th July Traffic lights will be removed, however Hampshire County Council will be working on Burnetts Lane
30th July onwards – We shall be closing Burnetts Lane to allow work on the tie in to the new road and roundabout. Resident access will be maintained for 7 weeks.
UPDATE:
The new dates for the closure will be for two nights, Wednesday 27th January 2021 and Thursday 28th January 2021. The road will be closed from 8pm through to 6am.
allington road closure january 2021_update
Allington Lane road closures over night to commence 18th and 19th January for tie in for North and South of new carriageway
18th is for North bound tie in
19th is for southern end tie in
Works will include planning out and installing binder.
Please see drawings below for the diversion route for Allington lane closure for 18th & 19th January 2021 closures and the 28th January.
We will be closing Allington Lane from Fir Tree Lane through to Allington Lane Nurseries on Thursday 1st October 2020 from 0730 till 1630 to allow us to relocate the overhead power lines.
One Horton Heath: Segments 1 and 2 Road Infrastructure – Road closure
Eastleigh Borough Council is building a new development, called One Horton Heath, to the west of the present Horton Heath set in 310 acres running alongside Burnetts Lane and Chalcroft Business Park to the South and Allington Lane to the North.
The works are progressing well and we are now preparing to relocate a set of overhead electricity lines to underground. To allow us to do this, we will be closing Allington Lane, from Fir Tree Lane through to Allington Lane Nurseries on Thursday 1st October 2020 from 0730 till 1630.
Please see diagram below to show the road closure and associated diversion. This diversion will be clearly signed.
To allow us to prepare and then complete the works there will be temporary traffic lights in place on this section to work on one lane for a period of 9 weeks from Tuesday 1st September 2020.
To keep up to date on each stage of the build please visit the One Horton Heath Mildren community information site: www.community.mildrenconstruction.co.uk
Other contact details:
- Mildren Helpdesk number; 03300 130 214
- Email; onehortonheath@mildrenconstruction.co.uk
There will also be local road user signage in place. More information about One Horton Heath and how to contact us can be found at www.onehortonheath.co.uk
Sincerely,
One Horton Heath Team