Please see below for information regarding our latest works, these will be updated every two weeks.

Monday 21st September 2020

The narrow lanes have been installed on the A22 and as from Monday the 21st there will be full closures Monday to Friday from 8pm to 5am so the new layby can be constructed. Daytime works will also continue with the mainline drainage also starting. All in all good progress is being made so lets hope this dry weather keeps up.

Monday 17 August

With the earthworks on the main site nearing completion, we have now started the first phase of works on the A22. The layby is being removed during off peak hours – 9:30 till 15:30 each day and will be controlled by two way traffic light for the next two weeks. This will enable the traffic to flow whilst we install the majority of the kerbs and drainage on the proposed carriageway.

Monday 10 August

The layout of the new road is starting to take shape and most of the material has been shifted from the main site to the landscaping areas. The slope drainage has now started and the fill adjacent to the A22 is well underway

Starting Wednesday 29 July

The earthworks element of the contract have progresses well in July and we are fast approaching the next phase of works to remove the northbound layby on the A22. In order to undertake these works, the speed limit will be reduce to 30mph and off peak traffic signals will be installed on the 17th August 2020 for approx 3 weeks.

Starting Tuesday 30 June 2020

We are currently working on the following:

  • Topsoil strip site wide
  • Commence with the embankment cutting to a 1 in 8 profile
  • Commence construction of stockpile no 1

Looking a head we will be working on:

  • Embankment drainage

Tuesday 23 June 2020

Earthworks will continue for the month of July. We will be cutting material to form the slopes and moving the surplus material to designated stock pile areas.